IAM Program Highlights

 

<< What's Happened

What's Next >>

2014:

  • Information gathering

 2015:

  • Product demonstration

2016: 

  • 18-month groundwork and information gathering summary submitted to CIO with recommendations
  • Engagement of consultation services from Integral Partners, LLC to develop a strategic roadmap and perform a gap assessment
  • Onsite staff workshop conducted with Integral Partners consultants for RFP Development
  • Request for Proposal Documentation
  • RFP draft documentation in final stages
  • RFP publication

2017:

  • Banner Enterprise Identity Services (BEIS) testing and implementation
  • RFP award - Product purchase (target June)

2018:

  • Server Provisioning Request
  • Directory server configuration
  • Implementation of the product -- development, test, and production builds
  • Testing
  • Application connector development
  • Configuration and product build
  • Training

2019

  • User Acceptance Testing
  • Migration to the Production system and Legacy load
  • Vendor-Onsite 
  • Go-Live
  • Post-production issue remediation

 

2020

  • Migrate CAS